Onboarding 1,200+ Devices in 5 Days at 20-22 Ropemaker Street

Overview
20–22 Ropemaker Street is a flagship commercial property delivered with a smart enablement scheme designed to provide a connected operational layer from day one.
For the portfolio customer, the enablement contractor selected its own preferred mix of technologies — from transport protocols to data models, naming structures and client connectors. The challenge was to bring that varied technology stack into one operational platform without slowing the development programme.
The connectivity challenge
Connectivity is often the bottleneck in smart building projects. Many platforms expect a narrow set of protocols, data structures or naming conventions, leaving project teams to spend time reworking systems before the building can become operational.
At Ropemaker, the selected technology approach was already defined by the enablement contractor. Attain needed to work with that approach rather than force the project into a single standard.
The Attain approach
Attain is designed to accommodate a wide range of building connectivity approaches. Once the project documentation was uploaded, the client connectors automatically adapted to the available data and naming structures.
This meant the project team could connect the building’s devices and systems without having to redesign the contractor’s preferred technology stack. The platform became operational around the building, rather than requiring the building to be reshaped around the platform.
Result: 1,200+ devices onboarded in 5 days
The result was a rapid onboarding process: 1,200+ devices were connected and the platform was fully operational within five days.
Commissioning during the soft landings period
Connectivity was only one part of the challenge. During the building’s soft landings period, the site team needed a more effective way to manage snagging and de-snagging works.
Rather than separating fault discovery, task management and completion checks across different tools, the team centralised the process in Attain. The platform’s fault detection and diagnostics engine identified conditions that could be treated as snags, while the remedial workflow kept the work visible and organised in one place.
Completion could then be checked against live operational data, helping the team validate that a remedial action had actually resolved the underlying issue.
Results
The commissioning workflow gave the site team a clearer, more continuous view of progress:
Snagging reports were generated automatically every day.
Faults, remedial actions and completion checks were managed in one operational workflow.
The site team gained faster visibility of outstanding de-snagging work, helping reduce the volume of open snags.
What this demonstrates
Ropemaker shows that smart building delivery does not have to be constrained by a single connectivity standard. When the platform can adapt to the building’s chosen protocols, data structures and naming conventions, the project can move from enablement to operational use much faster.
It also shows the value of carrying that connected data into commissioning. The same platform that brings devices online can help site teams identify snags, coordinate remedial work and verify completion during the transition into day-to-day operation.
For complex flagship buildings, the combination of adaptable connectivity and operational workflows can turn smart enablement into a practical foundation for continuous performance improvement.